Worked example (hypothetical numbers): 1.2 m × (100 × 2 + 4) = 244.8 m² per belt; 8 × 5 = 40 belts; 9,792 m² ≈ 9,800 m², 8,160 linear metres.
Inputs
Where the numbers come from
- 01
Width
Cage drawing (no universal width).
- 02
Row length
Tape or drawing; if rows differ, calculate each.
- 03
Tiers & rows
Count the tiers; take the number of rows from the drawing.
- 04
Allowance
Wrap around drive and idler rollers plus take-up travel (the T/CAAA 152—2025 draft requires at least 400 mm of tension adjustment at the idler).
Rough sizing
Only know the flock size?
You can only estimate the order of magnitude. At 450–540 cm² of cage floor per hen (MARA), 100,000 hens need 4,500–5,400 m² of cage floor; with the return run, belt quantity is roughly 9,000–10,800 m². Order from the drawing, not from this estimate.
FAQ
Questions buyers ask
Why multiply the row length by two?
A manure belt is a closed loop: the upper run carries manure and the lower run returns, each the length of the row.
Is belt area just row length × width?
No — that is only the upper run of one tier. Use width × (2 × row length + allowance) × tiers × rows.
Should I add an allowance?
Yes. The belt wraps around both end rollers and needs take-up travel. Take the figure from the cage drawing.